From: Tommy Healy
Date: 28 Sep 2001
Time: 11:40:16
Hi Stan! Thanks for the quick turnaround with your reply. It seems to me that by using AQL or RQL etc I am specifying acceptable quality levels and working to that.{Prob of accepting / rejecting parts etc..}
What happens if I ask the following:
"A company produces x units per yr. They must validate a change in the process. How many units should be built and tested to accurately represent a build of x units. "
Is this a slightly different approach?? Can this be solved by a table or plan? Perhaps there is a simple rationale to apply to my question and I just can't see / understand it.
Again many thanks. There is certainly a lot of valuable information here.
Tommy