How to deal with small lot size

From: dwang@afop.com
Date: 20 Jan 2003
Time: 14:04:38

Comments

Hi,

I am studying on OEM parts inspection model. All the parts can be numerically measured (can use inspection by varible?)

Usually, about 100 parts come in one month, are divided into 4-5 batches. For example, 10 for 1st week, 20 for 2rd week, 40 for 3rd week, 30 for 4rd week. We have to ship out parts asap. Say, can not wait for all 100 parts ready to form a lot to test.

What we want is to set up a procedure to sample the OEM parts and keep a confidence level.

I studied continuous sampling plan. But we can not have the full inspection done.

Do you guys have some advice? Many thanks.